Painted dive towers and back wall. Glass installation on dive towers.
Duct work, Lighting and ceiling grid system installation in the lobby.
Esplanade entrance panel and lettering installation.
Paver installation at the top of the site stairs. These narrow pavers match pavers used in the Phase I design.
50 M pool Ceiling grid completion, speaker system and fabric duct completion.
Perennial garden and seating area.
HDPE bench installation. 50M pool spectator seating.
Front entrance paver installation.